Reorder planning, when plant stock falls below reorder point procurement
is triggered. Planning can be done by manual or automatic.
We maintain reorder point in Material Master when warehouse stock reaches
this level, MRP will trigger procurement for the same.
AND reorder point planning is used for consumption based planning.
For re-order point planning, you have to put some field in MRP1 View
of the Materail Master.
MRP Type: VB (manual reorder point planning)
Reorder Point: for example 100 ( the level of stock at which u want
to trigger replenishment)
Lot Size: HB (maximum replenishment) / or u can maintain EX / FX also.
but it advisable to go with HB
Maximum Stock Level: for example 400 (as per ur requirement)
For re-order point planning, you can leave blank strategy.
Get help for your SAP PP Problems
SAP PP Forum - Do you have
a SAP PP Question?
SAP Production Planning Books
SAP PP Certification,
Interview Questions and Configuration Books
SAP PP Tips
SAP PP Tips and Production Planning/Control
Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.sap-img.com
All the site contents are Copyright © www.sap-img.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.sap-img.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.sap-img.com or the content authors.
|