What Is The Rescheduling
Horizon
The planning horizon is the number of days where MRP will be running.
Now, in the IMG, in the Maintain plant parameters there is a button for
Rescheduling for specific plant. What is the rescheduling horizon?
There are certain elements such as firm planned orders, PO, firm purch
reqs. etc that are considering in here but what is the rescheduling horizon?
What does it do?
By: Sankaran
The below info will help you to understand the Rescheduling Horizon
concept:
Rescheduling Check
An important group of the exception messages mentioned above are the
rescheduling proposals. In the net requirements calculation, the system
checks whether warehouse stock or firmed receipts are available in sufficient
quantity to cover requirements. If a material shortage exists, the system
usually creates a new procurement proposal. The rescheduling check is used
to change the dates of already existing firmed receipts not planned on
the same day as the requirement to suit the requirement date. For this
purpose, the system displays the appropriate exception messages with rescheduling
proposals for these firmed receipts to be processed by the MRP controller.
Prerequisites
You have defined the rescheduling parameters in Customizing for MRP:
per plant in the IMG activity Carry out overall maintenance of plant
parameters
per MRP group in the IMG activity Carry out overall maintenance of
MRP groups.
The rescheduling horizon, which defines the period for bringing forward
the receipts, and the receipt elements, which should be taken into account
in rescheduling, are included in these.
You can also define tolerance values for the creation of exception
messages, in Customizing. These values define a time period in which no
exception message is to be created, despite the fact that a rescheduling
proposal may exist. The MRP controller can thus avoid a situation where
too many exception messages are created if a certain buffer has already
been planned for scheduling basis dates.
Process Flow
Bring process forward (reschedule in):
Within this rescheduling horizon, the net requirements calculation
checks whether, after a requirement, a firmed receipt exists, which can
be used to cover this requirement. Then the system displays a rescheduling
date as well as the exception message Bring process forward for this receipt.
The net requirements calculation then uses this receipt and the system
will only create another procurement proposal if the receipt quantity is
not sufficient to cover the complete requirement. Several firmed receipts
can be used to cover one requirement.
The rescheduling horizon is always calculated from the MRP date.
Postpone process (reschedule out), or cancel process:
The net requirements calculation checks over the complete time axis
whether availability could still be guaranteed without the receipt in question.
If this is the case, the system checks whether the receipt planned here
could be used to cover a future requirement. If the system can find such
a requirement, it then displays a rescheduling date as well as the exception
message Postpone process for this receipt.
If the system finds no future requirement, for which the receipt is
required, the system displays the exception message Cancel process.
Get help for your SAP PP Problems
SAP PP Forum - Do you have
a SAP PP Question?
SAP Production Planning Books
SAP PP Certification,
Interview Questions and Configuration Books
SAP PP Tips
SAP PP Tips and Production Planning/Control
Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.sap-img.com
All the site contents are Copyright © www.sap-img.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.sap-img.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.sap-img.com or the content authors.
|