I have created a planned order thro MRP run, but reservation for
raw material is not created, even though stock is available. After conversion
to Production order reservation is created. After confirmation and goods
reciept MB31 final product is updated in storage location, but raw material
quantity is not reducing.
PART I After MRP run, based on the demand Planned order will be created and for the BOM components sytem will create dependent requirement if stock is available. If stock is not available system creates a planned order or a purchase requistation. Once the planned order of the Header material is converted into a production order , then system converts the dependent requirement into reservations. PART II After confirmation and goods reciept if the item components are not consumed, it means you have not defined backflush process. If you want to issue manualy to the order u can use T-CODE MB1A, for the same. K. Prasobh 1. Check backflush indicator either in routing /workcenter or in material
master.
Fast Links:
SAP PP Books
Best regards,
All the site contents are Copyright © www.sap-img.com
and the content authors. All rights reserved.
|