Appreciated if some guide can be provided.
It is known that with this setting, material are always bring in
on the first working day of the month.
When MRP completion, the PR item shown 1-10-2004 290 pcs, is that
any possible to bring in material just right before dependant requirement
26-10-04 say about 24 or 25 of the month.
Any comment are welcome. In that case you might like to consider lot size key WB (weekly). It will bring in material at the first working day of the week. In your case it is Oct 25, 2004 But in this case, I will have increase administrative cost on monitoring
the material lot weekly.
How about manually change delivery date in PO item Check your config. in OMI4 - scheduling may by ''1'" for Lot size
of MB.
Friend PPS is correct, Schedule the "REQUIREMENTS DATE = DELIVERY DATE" option in Customizing for Lot Size MB (use Blank instead of 1) & your reqt 'll be met... We have similar problem and when I applied your solution, the proposed requirement date is perfect. Fast Links: