Interview Questions and Anwsers
on SAP PP
1. If you have released Prdn order today and it had gone to
shop floor. Next day it was found that there is shortage of material.
What will you?
2. How you define Standard Cost and Variable cost in PP?
3. Where can you find Read PP Master in SAP(PP)?
4. What are all the settings done for configuring integration
of PP with FICO?
1. Do availability check. You will get missing parts list. Procure those
missing parts. Then confirm the production order. One more thing you can
do, change customize setting so that user cannot release if parts are missing
during order release.
2. Standard cost is the cost which is fixed for a period, variable
cost is varying with period. As for example cost of semi finished, finished
materials are fixed & cost of raw materials are varied.
3. You will find in master data tab page of production header
data overview, CO02 - Read PP Master Data. Also from Functions menu you
will get Read PP Master Data. This means that you want the system
to re-update the production order with the latest BOM structure.
4. Assigning of Cost center to work center. Assigning Activity
type to work center, Standard Cost estimate, Costing Run, Order settlement,
Product costing. *-- Chandan Majumdar
---
1. Can MRP be carried out for one particular
level of a bom ( Level code : 0001/0002 etc).
Yes it can be done by
running for specific materials (Single Material Single Level)
2 How Requiements( PIR,Sles Order,
Customer Requirement) are reduced after they are produced?
Reqmts are reduced automatically
after Delivery is made to the Particular Order
(In case of Strategy
11, the PIRs are consumed after the GR for Production Order)
3. Can't one material be assigned to
more than one operation in a routing?
One material from a
BOM CANNOT be assigned to different Operations.
It can be done by defining
the material for so many times as required in the BOM
4. How to insert an inspection checkpoint
at the end of an operation?
If in process sample
is to be defined, assign inspection type 03 in the Material Master.
Then create MICs and
assign them in the Routings.
System automatically
generates the Inspection Lots
5. Where we have to specify the teardown
time in one operation?
Teardown time can be
defined as one of the Standard Parameters...
6. How the process time is calculated
in a WC when both labour, Machine categories exist?
Scheduling is done based
on the Capacity Category we define in the Workcenter
7. How to create opbject dependencies
in a BOM FOR A CONFIGURABLE MATERIAL?
Go to Extras -> Object
Dependency -> Assign
For this U need to create
Characteristics and Class (of Class Type 300) earlier
8. Can any body explain me why work scheduling
view is required for semi finished and finished products?
(Because we'll mention
all details in MRP views)
A) We need to maintain working scheduling
view in order to make that finished or semi finished goods available for
production as
we assign production scheduler and production scheduler profile in this
view, if not maintained
conversion of
planned order to production will not be possible.
Tips by : Nayak
SAP PP Q & A
SAP PP Questions and
Answers
Get help for your SAP PP Problems
SAP PP Forum - Do you have
a SAP PP Question?
SAP Books
SAP PP Books -
Certification, Interview Questions and Configurations
SAP PP Tips
SAP PP Tips and Production Planning/Control
Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.sap-img.com
All the site contents are Copyright © www.sap-img.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.sap-img.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.sap-img.com or the content authors.
|