I am trying to configure the range of coverage
profile to provide a 6 months safety stock, in which the 'target cov' field
should be populated with 180 days, but the that field only accepts 2 characters
max. Is there another way of accomplishing this or am I doing something
wrong. Please let me know. The current setup is:
- Period Indicator = M (Month)
- Type of Period = 1 (Workdays)
- Range of coverage in the first period:
- Min = blank; Target =
90; Max = blank
In this Target value accepts only digit numbers.
Muthu Chinnadurai
Yes the system accepts only two digits.
But since you want stock coverage for 180 days. Use target as say
60 and the number of periods as 3 . Try it and keep us posted. But
the one other issue is the system calculates the dynamic safety stock.
It easy to calculate the stock for the first
period but for the later periods its difficult. So if later there
is a problem with the quantity then its difficult to calculate or cross
check what system has proposed.
Raj
Using target as 60 and number of periods as 3, only results in system
maintaining safety stock for 60 days for first 3 periods. I found out that
there is no way out of this. Strange that SAP wouldn't let the companies
plan for inventory coverage more than
99 days. This is a pharmaceutical client whose procurement lead times
are more than 5 months for some of the materials, where they want to maintain
a 6 month coverage and SAP wouldn't allow to achieve it. Am I doing something
wrong here. Is there another way of maintaining dynamic safety stock for
180 days requirements coverage? Please share your knowledge.
Muthu
Please let me know in details how the profile coverage works in SAP.
In details means how it is being calculated and what is being considered.
As I am figuring how I could make use of this function that my customer
require us to keep 15 days inventory and customer forecast flucuates drastically
every week.
Thanking all in advance for your kind advice and help.
Alicia
In customizing in MRP calculation menu , you have Range of coverage.
Define the range of coverage you want , as you said 15 days for a period
of 3 months. Then in the profile first fill the Avg. daily req data
and then the range of coverage data.
Use this profile in the material master mrp II view(I think), in range
of coverage.
As far as calcualtion are concerned its very to calcualte the Qty for
the first period and then for the later periods its difficult.
May be I am wrong, just try and keep us posted
Raj
The Range of Coverage profile is define specific to a plant in IMG and
then assigned to materials in master data MRP 2 view. To define the profile,
use menu path
IMG->PP->MRP->MRP Calculation->Define Range of Coverage Profile. In
the definition, there are two sections of data that you need to fill in.
1. Parameters for calculation of average daily requirements and Period
indicator.
2. Minimum, Target, and Maximum stock calculation parameters.
PARAMETERS FOR AVERAGE DAILY REQUIREMENTS CALCULATION:
Choose the period indicator as Month, Period, or Week.
Specify the number of periods. This is used by system to calculate
the average daily requirements.
Select the "Type of Period Length", ie. as workdays or calendar days
or standard days (days per period). If the type of period length is selected
as standard days, they you have to specify the "days per period". Using
these three parameters, the system calculates average daily requirements
using the formula:
average daily requirements = Sum of requirements in the number of periods
/ number of days in the number of periods.
PARAMETERS FOR TARGET STOCK AS DAY'S OF SUPPLY
Then you have to specify how many workdays of supply you want to maintain
as target stock, in your case 15 workdays. If you wanted to maintain a
constant 15 days of supply as inventory through out the planning horizon,
just specify the target stock as 15 days and leave rest of the fields as
blank, i.e min, max, and number of periods. The number of periods in this
section simply maintains the target stock for that many periods from the
date of MRP run. This way you can tell the system to maintain different
target stock levels for three different period intervals. For example,
if you wanted to maintain 15 days stock for first 3 periods, then specify
the target stock as 15 days and number of periods corresponding to it as
3. The system then will maintain 15 days supply as inventory for first
3 periods from the date of MRP run and subsequent months zero inventory
will be maintained. This will allow you to maintain your 15 days supply
constantly for 3 periods.
Muthu Chinnadurai
Fast Links:
Get help for your SAP PP Problems
Do you have a SAP PP Question?
SAP PP Books
SAP Production Planning
Reference Books
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.sap-img.com
All the site contents are Copyright © www.sap-img.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.sap-img.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.sap-img.com or the content authors.
|