Can anyone please explain me the how the Costing takes place for the Production Orders. Actually, I am new to this package , In Other
Package (RAMCO ERP)
The following are considered in costing,
2) activity you have performed in terms of labour
hours that you entered while confirming the order (the rates for the labour
are defined in the activity planning tables of controlling module)..which
is generally associated with a formula key and attached to a workcenter
that is linked to a cost center also
Anil
Costing updation in production order How is costing updated for production order?
Planned cost is caculated if you click 'cost calculation'
in production order. GI go production order will update actual material
cost. Confirmation of production order will update actual activity cost.
You can settle cost once production order has status TECO or DLV. From
PP side, the transction is CO02
In IMG we can define that when we calcu. the planned cost. There are 3 ways.
But the actual cost is posted when we draw the
material, when we confirm the order......We can use co02 and click the
calcu. cost to update the cost in the prd order.
Error in Cost Calculation I am using 4.7. When I was saving my production
order, there was this error message that told me that there was an error
in cost calculation. Do you have any suggestions what I couldn't have done?
What can I do to fix this?
Check the log file in the Production Order -> Goto -> Logs -> For costing Then take it from here.... Check whether the material for which you have created a production order has a price define in material master like Moving average price or Std price. Fast Links:
SAP PP Books