Regarding Production Order Confirmation
Production order confirmation with future date
is not allowed
Future dates can be configured in the confirmation configuration.
In configuration OPK4, define confirmation
parameters.
When this configuration comes up, in the "Checks"
Sections, the last parameter says
"Date in the future."
Check this box if you want your dates in the future.
It determines whether dates in the future can be used in a confirmation.
If the indicator is not set, you cannot make any confirmations using
dates in the future.
If you try to do so, the system will issues an error message.
What is the importance of Production Order confirmation? Is there
any specification to use type of confirmation ie., CO11 or CO15 or CO11N
?
A confirmation documents the processing status of orders, operations,
suboperations and individual capacities.
You can enter a confirmation
- For an Opeartion (co11/co11n)
You have the following options:
- To confirm quantities, durations, activities or personnel data.
- To make a confirmation at a particular point in time (for example,
at the start of setup or the finish of processing) enter a
confirmation.
- When you confirm time events, the system calculates the required
duration. For example, the setup duration is the time between setup start
and setup finish.
- For an Order : CO15
If you enter a confirmation at order header level, the system confirms
all the operations that have a control key in which
confirmation is optional or necessary. The quantitiesconfirmed in the
operations are proportional to the quantities confirmed in the order header.
*-- Rajesh
I want to stop the confirmation of production order whenever there
is no goods issue to the production order so that I can get the correct
material accounting report. I can't set backfliush indicator to the
material at Routing level because we are handling the raw material
in batches, so I have to assign the batches to issue the raw material.(
tcode CO27 ).
We have set the criteria to release the production order is only
availability of raw material in plant, so system checks only the availability
of raw material & releases the order. Is it possible after
issuing the raw material the release of order took place?
Goods issues before release of order is not possible in SAP.
You can think of following things.
1) In opj4,you can block release of order if it has missing parts.
2) By using 'user exit' it is possible to disallow confirmation if
goods issues are not posted against each component.
*-- Shailendra
Get help for your SAP PP Problems
Do you have a SAP
PP Question?
SAP PP Books
SAP Production Planning
and Control Certification, Interview Questions and Configuration Reference
Books
SAP PP Tips
SAP PP Tips and Production Planning/Control
Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.sap-img.com
All the site contents are Copyright © www.sap-img.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.sap-img.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.sap-img.com or the content authors.
|