Stop Complete Confirmation (IW41)
before (IW32)
Any way we can stop the complete confirmation (IW41) being done with
out doing (IW32)?
This will help you on your way forward:
In the SAP standard business model, if the user technically completes
the works order, the following consequences occur:
1. Any reservations for which goods issues have physically been completed,
but which have not applied in the SAP system, are deleted. There is then
no way of recording the consumption of spares against the appropriate works
order.
2. Any purchase requisitions that have not been converted into purchase
orders are deleted.
The system does not provide any warning that these deletions have taken
place. Furthermore, since the system permits simultaneous completion of
multiple works orders (via IW38) there is a tendency to blindly close these
works orders without adequate reviewing.
Because of these issues, I suggest the following method:
Block technical completion where there is any work planned and this
has not been progressed to a point of final confirmation completeness;
this process can be further enhanced by checking that key details on the
related Breakdown/Unplanned Notification are complete.
This can be achieved by user exit "exit_saplcoih_004" when trying to
do the TECO via IW38, which broadly proceeds as follows.
1. Evaluate the works order plan against actual confirmations,
and determine if the activity is complete in quantity or by explicit completed
flag.
2. Check the required fields on the breakdown/unplanned or call-out/after
hours notification.
3. Confirm that no part of the tests in 1 and 2 failed. Where
the works order and notification have failed, a report can then be generated
explicitly defining all activity and information that must be completed
in order to achieve technical completion.
4. If the user is allowed to override this block block, and elects
to do so, then the order is closed according to the SAP standard method.
This method clears open reservations and any purchase requisitions which
have not been converted to purchase orders. I suggest a separate authorisation
for the override so that you can still achieve control via segregation
of duties.
The following Business rules need to be met for successful technical
completion and should to be coded into the user-exit via your ABAP developers:
For the Works order:
- Internal operations: All final confirmations are required, or, if
the operation is not to be completed then it is to be deleted.
- External operations and spares procurement: All purchase requisitions
must be turned into purchase orders, which must be goods receipted. Alternatively,
if the external spare or item of labour is no longer required then the
PR, together with any follow on PO must be deleted.
- Internal spares: All reservations must either have the final goods
issue completed or those items not required for the completion of the works
order must be deleted.
For the Notification:
- Only applies to breakdown/unplanned and call-out/after hours notifications.
- Check that each of these fields is complete: the Breakdown flag,
malfunction start and end date and time. For related Catalogs details
for the Notification (if you are using them):
- For notification item number 0010: Check that the following
fields have been completed: object part, failure code or text.
- For each of the notification causes: Check for a cause that
is not deleted. Check that the code or text field is complete.
- For each of the notification activities. Check that each activity
is complete.
To help your developers, the following tables will need to be accessed
while processing the user-exit:
AFKO PP order header
T430 Operation/Activity control key
AFKO PP order header
AFVC Operation within an order
AFRU Operation confirmations
VIAUFKS PM Order Selection View
MSEG Document Segment: Material
RESB Reservations
AFVV Operation times.
AUFM Material movements for order.
EBAN Requisition items
EBKN Requisition items Account Assi
EKPO Purchase order
EKBE Purchase order history
EKKN Purchase order Account assign
JEST Object status
QMMA Quality notification activities
QMEL Quality notification
QMFE Quality notification items
QMUR Quality notification causes
QMIH Quality message maintenance data excerpt
IFLOT Functional Location
EQKT Equipment short texts
SAP PM Tips by : Gordon
Fast Links:
Measuring Docs Against Work Orders
Recording
Measuring Docs. Against Work Orders
Have a SAP PM Problems?
Do you have
a SAP PM Question?
SAP Books
SAP Certification, Functional,
Basis Administration and ABAP Programming Reference Books
SAP PM
SAP PM Tips and Plant Maintenance
Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.sap-img.com
All the site contents are Copyright © www.sap-img.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.sap-img.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.sap-img.com or the content authors.
|