Can somebody give me definition and it's formula for calculation
of the following terms:
1. Equipment Uptime
2. Equipment Efficiency
3. Equipment Effectiveness
Vivek.K
The question is too vague to give a precise answer. Uptime, Efficiency
and Effectiveness will depend on how you have defined these terms, what
sort of plant/process you are measuring and how you measure them in practise.
Having said that, here is an attempt at answering your question
1. Uptime is the total time that a machine or process is available
to perform its function.
UPTIME = Total Time Available - Downtime
Downtime consists of both planned and unplanned
events.
2. Equipment Efficiency - What do see as the difference between
2&3?
3. Equipment Effectiveness as defined by Overall Equipment Effectiveness:
OEE = Availability Rate x Performance Rate
x Quality Rate
Availability Rate = %Uptime of Total Time
Performance Rate in most cases is related to Mean Speed as a percentage
of Max. Speed. Utilisation is also a concept that fits into this category.
Quality Rate is an expression of Good(conforming/saleable) products
as a percentage of total products made.
A, P and Q are all efficiencies in their own right.
Hope this helps.
Wayne
Fast Links:
Have a SAP PM Problems?
Do you have
a SAP PM Question?
SAP Books
SAP Functional,
Basis Administration and ABAP Programming Reference Books
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.sap-img.com
All the site contents are Copyright © www.sap-img.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.sap-img.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.sap-img.com or the content authors.
|