| Control Maintenance Budget in
PM
The way to control maintenance budget in PM.
by : Santosh Satapathy
Maintenance budget
1) Hi, I just see some desperate attempt to know
about maintenace budget and control but I hope can clear you all.
Budget and control of order can be done to all the order type of sap pm
orders functional background
As we know when creating equipment in maintenance
master data we are using two work centeres one is location work center
and the other one is responsibile work center. The location work
center describes the line or area or section of production the equipment
belongs and in the order the work center we maintain it maintains the cost
per activity we define.
Suppose our maintenance team goes and do some
work, say for two hours, so for this activity type what is defined in the
controlling will be debited from the production line or section or area
as it is maintained in pp. Of cousre when we settle the order and
at the same time from the budget that much of fund deducted
Integration Part
a) actually this is done by co people
b) go to trans koab
c) tick the commit management in control indicators
maintain co-partner as semi
active
you can maintain other things
as maintaenance status and settlement profile
d) you should maintain object class as overhead
costs orif you have service module you can do profitably analysis
e) you must maintain collective order without
automatic goods movement
f) you can maintain status profile as your wish
g) for residence time i amintaied one month
2) then you have to maintain budget profile
for maintaining budget profile
you have to goto trs ok0b
crate a budhet profile these
are co people job
3) go to oioa here you assign budget profile
to order type
4) in mantain budget profile
time frame -past means
how many years past you can plan here start year is the referenace
point
same with future
you must tick total
values
annual values
exchange rate should
be m-standard translation at average rate
activation type should
be 1-automaticactivated when budget allocation done
budgeting currency-i
choose controlling currency
5) then go to ko22 and assign the budget profile
to order or group of order
This is the way I maintain budget for pm orders.
Have a SAP PM Problems?
SAP PM Forum
- Do you have a SAP PM Question?
SAP Plant Maintenance Books
SAP PM Books - Certification,
Interview Questions and Configuration
SAP PM
SAP PM Tips and Plant Maintenance
Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.sap-img.com
All the site contents are Copyright © www.sap-img.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.sap-img.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.sap-img.com or the content authors.
|