| PP/DS Heuristic Question
When executing a PP/DS Heuristic we want to plan only a certain amount
of products. In the selection criteria of the Production Planning Run (background
processing) we cannot enter the restrictions which lead to the desired
scope of products to be planned (Propagation Range, Object 'Products' are
not sufficient). Somehow we want to base the selection of
In our Heuristic run no PPM explosion takes place, only externally procured products are planned. Does anybody know a solution for this selection issue?
You will need to set the object type for selection to 5 - Copy objects from customer exit APOCDPS1 This will allow you to use the customer exit to select the objects you require via ABAP.
Part number strategy As we consider moving to R/3 globally and then implement APO we are
struggling with part numbering strategy. Without APO in place is
there a way to allow different countries (different company and plant in
our case) to maintain unique part numbers and still accomplish inter-company
stock transfers? Or do we need APO for this and, therefore, need
to force a
I do not know how you can accomplish this w/o APO, although you may
be able to.
With APO each R/3 instance can use the same part number aslong as each
uses its own Business System Group. You will need to modify
CIF a little, but it should work.
In KC we have a unique part number trough Latin America for finished
products, semielaborated and raw materials. Implement this is very
hard because you need a team of master data that all countries because
first you have to prepare all the codes that you go to upload, then you
have to standarize the codes with a unique part number. For us is
useful overall in
Best regards,
|